An injection molding machine commissioning checklist should answer three questions: Is the site ready? Can the machine, mold and auxiliary equipment run together as planned? Can the production team reproduce the approved result after handover? A first molded part is a useful milestone, but it does not show whether the process will hold over an agreed production run.

DAYA Machinery documented the installation and production start-up of a DAYAMAC DYM350, a 350-ton injection molding machine, at a customer’s factory. The site photo shows the installed machine and material-handling equipment beside it. The original installation report and video show the start-up; they do not publish cycle time, scrap rate or a signed acceptance record. The checklist below is for planning your own project.

DAYAMAC DYM350 injection molding machine and material-handling equipment at the customer’s factory
DAYAMAC DYM350 on the customer’s factory floor. Photo from DAYA Machinery’s original installation report.

1. Confirm site readiness before the machine arrives

Ask the supplier for the layout and utility schedule for the actual machine configuration. The footprint alone does not tell you whether there is room to move the mold in, open a service panel or access the injection unit. Confirm the unloading route, lifting plan, floor requirements and service clearances with the installation team.

  • Power and utilities: Confirm supply and grounding requirements, cooling-water supply and return, and compressed air if the cell needs it. Assign an owner and a due date for each connection.
  • Mold fit: Check mold dimensions and weight, tie-bar clearance, mold height, opening stroke, ejector requirements and the nozzle-to-sprue interface against the machine drawings.
  • Auxiliary equipment: List the loader, dryer or hopper, mold temperature controller, robot and conveyor that the job actually requires. Agree who supplies and connects each item.

2. Plan a trial with the mold and resin you intend to run

Have qualified personnel verify installation and safety functions according to the machine manual and site procedures. For the trial, identify the mold and cavity layout, the resin grade and the peripherals. If substitute resin or a different mold is used, record the change so the trial is not mistaken for acceptance of the intended production setup.

Once conditions have stabilized, record the recipe version, actual cycle time, sample count and rejected parts. Check the dimensions and appearance that matter for the drawing or approved sample. For a multi-cavity mold, record samples by cavity so one poor cavity does not disappear into a batch average. Keep the samples with the trial record so the next shift can compare its output.

3. Agree on site acceptance before the run starts

Factory acceptance testing (FAT) takes place before shipment when specified. Site acceptance testing (SAT) checks the agreed scope after installation, with the utilities and equipment at the receiving plant. Define the test method, run length, tolerances, reject criteria and who signs off before the trial. If your process must recover after a planned stop, agree on a restart check as well.

CheckpointEvidence to keep
Installation readySigned utility and installation checks, plus an open-issues list
Trial readyMold ID, cavity layout, resin grade and the peripherals actually used
Run acceptedRun duration, measured cycle time, accepted and rejected counts, and approved samples
Production handoverRecipe backup, operator briefing, maintenance documents and owners for any unresolved items

What to send DAYA before ordering or commissioning a machine

Share your part drawing or sample, resin grade, target output, mold dimensions and weight, cavity count, and the utility information for your site. If you already have a machine in mind, include the model and which auxiliaries you plan to reuse. These details give the supplier enough information to discuss mold fit, trial scope and which acceptance criteria belong in the quotation.

Contact DAYA about your installation or trial requirements, or explore DAYA’s injection molding machines.